Management procurement systems

11/04/2017 02:26

In this arrangement the client plays an active role in the procurement system by entering into separate contracts with the designer (architect or engineer), the construction manager, and individual trade contractors. The client takes on the contractual role, while the construction or project manager provides the active role of managing the separate trade contracts, and ensuring that they all work smoothly and effectively together.

Management procurement systems are often used to speed up the procurement processes, allow the client greater flexibility in design variation throughout the contract, the ability to appoint individual work contractors, separate contractual responsibility on each individual throughout the contract, and to provide greater client control.